Monday, 10 October 2011

A roof over our heads






It's all quite exciting at the moment: we're starting to see the results of there being five builders on the job. The wooden bases of the roofs are now in place (90% done in the photos), and we've now bought some of the policarbonate and a few sheets of Onduline, ready for when Horacio gives the maestros the thumbs up.

Saúl has been working on the north-facing balcony at the top of the house, which gets some lovely afternoon sunshine.

October brought with it a bunch of workers and some diggers. We hadn't realised how wide the track (road-to-be) is. Hopefully it won't look like a motorway anytime soon!

A belated late-September post






Plenty going on at the moment - the beans and peas seem very happy, Daisy has sorted out some plants to edge part of the path at the back, all the roof beams are in place and we've started planning bottle arrangements for some of the walls.

The upstairs back bedroom is going to end up having a rather nice high ceiling. Steve was particularly happy with the photo of Leborio's foot.

Saturday, 17 September 2011

The Pre-Columnas Age





We've planted eight trees so far, four of which are on our land - the others are on the land next door.

We managed to get my granddad up to the garage, but he wasn't too up for walking up to the house and from what he saw he wasn't too impressed anyway!

Celso is the new member of the team and has been working on preparing the columns on the water tank/veranda. They've been working seven days a week recently and tomorrow are planning on filling the cardboard pillars with cement.

The others are still working on the roof, which is going fine. Daisy and I measured up our milk carton sheets today, as we were told that we'll need a total of 43 square metres or so. Only fifteen to go...

Friday, 2 September 2011

Beam me up, Hector

































So as not to let the roof beams be exposed to too much rain, the builders are doing their best to move swiftly. A drill purchase later and after 3 hours scouring Xalapa for the right drill bits, Hector and co could start securing the beams into place.

We think it looks great!

It looks like the road will be getting tarmacked soon; we went to a meeting about it this evening and found out that together with the rest of the neighbours on the street we'll have to pay 10% of the job...

Tomorrow's job: plant four trees! A guava, a peach, a lime and an avocado.

Monday, 22 August 2011

Last post before the roof





It might seem like not a lot has been done over the past month, but it has been rainy season and the guys have been plastering quite a lot inside the house. It's gone up in height a bit too, ready for the roof. The room at the top (the study) is going to be stunning - it might be worth considering as a bedroom as views are great and you can almost see 360 degrees around you!

The garden is looking lovely and green. Ferns, beans, strawberries and a couple of young trees that we planted next door are all enjoying the sun and rain.

There's a shot here from the East angle - so that's the front door in the middle with the living/dining room on the left and the kitchen on the right, below the main bedroom and its balcony. You can perhaps appreciate just how much light (or how many windows) there's going to be, particularly up in the study.

The roof timber was delivered today so the next installment should be exciting!

Thursday, 21 July 2011

Gardening



We've also been taking advantage of the sunny days between the rains to do a bit of work in the garden.

Saturdays have been spent working on the path and filling in a horizontal terrace - in the long-run there should be at least two, if not three terraces, but it's hard work wheelbarrowing earth uphill!

I've also been relocating ferns - it's not to clear in the picture, but the sloping beds nearest the house are now covered in ferns. I'm hoping this will help to hold all the soil in place, as well as looking rather luscious.

There are so many pretty plants growing already, like this purple flower, that it almost feels a shame to bring in new plants. I think I'll try to reach a balance between what grows naturally and what would be useful and nice to look at. And first of all, trees and the like...

The current plan includes lemon/lime, guava, peach, avocado, macadamia nut, and black pepper... yummmmm.

In the Dog House





The neighbourhood dogs certainly seem to feel very at home in the house! Canica (the black dog) and her pal are testing out the kitchen, and have become very good at showing us the way up the stairs... Speaking of which, we now have stairs all the way up to the top of the house.

The builders are now just finishing off the walls at the top of the house - the stairwell, a study and a balcony that will look down the street.

On the garden side of the house, Hector is getting things ready to put the roof on.

You can also see the big arch in the living/dining room area. It's going to be a rather nice room with views up into the garden and plenty of light.

This week we've also been discussing kitchen fittings and a fitted closet for one of the bedrooms, which makes moving in feel that little bit closer.

Saturday, 18 June 2011

Pretty things




Second post today, but I was quite camera-happy.

The view out of our bedroom window is going to be pretty nice, as you can see here!

The water filters have been in place quite some time now and the plants are now looking very happy; we're looking forward to them flowering.

We often find ourselves parking at our favourite neighbour's (Hugo's!) and today we happened to notice his beautiful orchids.

How do you translate "colado", anyway?





Things are looking lovely at the moment - you can almost see the smiles on the plants when they get loads of rain and loads of sunshine in the same day. Yesterday the 4 builders and 4 helpers did the "colado" of the second floor (i.e. they put in the the second floor), as well as the reinforcing struts and arch - should look nice when those blocks are removed!

The view from the very top is great, although Daisy finds it too scary to walk to the edge! Fortunately Hector doesn't seem to get vertigo so he's been doing a lot of work perched metres up in the air as you can see in one of these photos.

There's a shot of the back of the house too; Daisy and I have been adding some earth to widen a flat space, ready for planting.

Word has it that the council is coming this coming week to start on the pavements in the street, and when they've done that they're supposed to be starting on the road... Fingers crossed!

Saturday, 14 May 2011

Upstairs























We are now the proud owners of a usable set of stairs. Even in rough concrete they look nice, but once they get some wood or tiles on them, they should be very pleasant to look at.

Having stairs also means that we now have very easy access to the first floor... as does the dog who came to inspect the building work on Friday! In the dog photo you can also see the arch that leads from the kitchen/living room to the stairs and the bathroom and bedroom at the back of the house.

Looking down from upstairs, you can start to appreciate the size of the windows in the living room area. It's still an open space at the moment, but there will, eventually, be a wooden mezzanine covering around half of this space, as is shown in the original plans

Wednesday, 20 April 2011

Moving up in the world



The past few weeks have seen a lot of visible change in the building work. With the floor set, the builders have been working on the walls of the first floor. Quite a view from up there!

We're a little concerned about how imposing the house might look once it's finished: there's still another mini floor to go, and it's already looking tall... The sooner we can get planting trees, the better!

Friday, 18 March 2011

And we have a first floor!






After a bit of a difficult time convincing the builders to get a grip and work hard, (after having caught them pretty tipsy during work hours), things have been moving on well recently and we had 8 on the go for one day in order to finish the cement work of the first floor, including the little overhanging balcony in the main bedroom.

The street is still a no-go area with a vehicle, (because of drainage works), so the guys recently had to take over a ton of cement up the steep track on their backs... Not ideal, but pretty impressive.

You can see the leaves in the bathroom ceiling; the idea is to peel them off leaving what should be a nice, subtle effect.

There's a shot of el Maestro Saúl applying a light layer of cement in what will be the living room.

It's all looking much more like a house now, I'm sure you'll agree!


Filters are done!



Posting this a bit late, but we took these photos on the 3rd March 2011.

Hector and co have done a nice job of the filters, they're looking good and working fine, or so it would seem so far. There are some plants living in one of the sections too.

Meanwhile the strengthening metalwork is getting sorted ready to take the weight of the cement floor, and to reinforce the walls.